Plywood and Composite Wood Products (PCWP)
NESHAP Summary
Main : 1 : 2 : 3 : 4 : 5 : 6 : 7 : 8
6. When Must Sources Comply With the Final Rule?
Existing
PCWP facilities must comply within 3 years of September 28,
2004. New sources that commence construction after January
9, 2003, must comply immediately upon initial startup or
on September 28, 2004, whichever is later.
Existing sources that wish to be included in the delisted low-risk subcategory
must receive EPA approval of their eligibility demonstrations no later than 3
years after September 28, 2004, or be in compliance with the final rule. New
sources that wish to be included in the delisted low-risk subcategory must receive
EPA approval of their eligibility demonstrations no later than initial startup
or on September 28, 2004, which ever is later, or be in compliance with the final
rule.
Main : 1 : 2 : 3 : 4 : 5 : 6 : 7 : 8
|
 |