7. How Must the The Source Demonstrate Compliance?
The source must demonstrate compliance by meeting the applicable
requirements in the EG/NSPS and, if the owner is required to install
a collection and control system, they must maintain monitoring parameters
within acceptable ranges. In addition, you must submit reports every
6 months which would include any notifications of deviations from
the monitoring parameter values.The source must develop and implement
a written SSM plan according to the provisions in section 63.6(e)(3).
If the operator takes action during a SSM event, they must keep
records for that SSM event which demonstrate that they followed
the procedures specified in the SSM plan. The source must submit
a report every 6 months if the action is consistent with the SSM
plan. However, if the action is not consistent with the SSM plan,
you must notify EPA within 2 days of the SSM event and must follow
up with a letter within 7 days of the event (section 63.10(d)(5)(ii)).