The University of Tennessee Institute for Public Service
A-Z Index / WebMail / Dept. Directory
Center for Industrial Services

MACT Rules

More Info




arrow

Industrial/Commercial/Institutional Boilers
and Process Heaters NESHAP Summary


Main : 1 : 2 : 3 : 4 : 5 : 6 : 7 : 8

8. What Are the Health-Based Compliance Alternatives, and How Do I Demonstrate Eligibility?

HCl Compliance Alternative
As an alternative to the requirement for each large solid fuel-fired boiler to demonstrate compliance with the HCl emission limit in the final rule, the source may demonstrate compliance with a health-based HCl equivalent allowable emission limit.

waterfall and pine treeTotal Selected Metals Compliance Alternative
In lieu of complying with the emission standard for total selected metals (TSM) in the boiler MACT final rule based on the sum of emissions for the eight selected metals, the source may demonstrate eligibility for complying with the TSM standard based on excluding manganese emissions from the summation of TSM emissions for the affected source unit(s).

If the source elects to demonstrate eligibility for either of the health- based compliance alternatives, they must submit certified documentation supporting compliance with the procedures at least 1 year before the compliance date.


Main : 1 : 2 : 3 : 4 : 5 : 6 : 7 : 8